Aquatic & Community Centers and Storm Water Infrastructure Programs

Parks & Storm Water - ½% Sales Tax




Proposition P Financing Status:

  • Prop-P - expected to generate approximately $1.19M annually for 20 years.
    • Revenue receipt history:  2008 » $1.239M     2009 »  $1.068M
  • Unobligated revenue balance from 2008:  $728K
  • Certificates of Participation (COP) sold:  $14.110M
  • True Interest Cost:  4.69%
  • Total Cost:  $20.240M
  • Net available for projects:  $12.667M
  • Funds Obligated for Aquatic & Community Centers:  $8.745M
  • Funds Committed for Storm Water Projects:  $3.294M
  • Uncommitted COP Funds:  $627K

Annual Revenue Required to Repay Debt:  $1.072M

Apparent Current Revenue Rate:  $1.038M

What are the approved Aquatic & Community Center Projects?

  • Aquatic Center
    • Competition & Dive Pool  (60' x 75')
    • Leisure Pool with zero-depth entry
    • Lazy River  (400')
  • Community Center
    • Parks Department offices
    • Meeting rooms
    • Multi-purpose room
    • Fitness Center
    • Gymnasium




Click here to Return